Green Light Contractors
New England Solar Farm Bulk Earthworks
Completion: June 30 2023
Contract Value: $15 million
Superintendent: Matt Reilly
About this Project
95,000m3 of bulk earthworks level 1 cut/fill operations
10,000,000m2 clear and grub operations
Field and geotechnical investigations to locate quality site won
subgrade placement materials
Substantial technical dewatering
40,000 m2 stabilized hard stand areas
32km of subgrade treatment ready for internal road construction.